An illustrative Swiss manufacturer uses temperature and vibration readings to bring unusual pump operating conditions to specialist attention earlier. AI prioritises observations; maintenance staff confirm causes and decide on interventions. The draft distinguishes condition monitoring from actual failure prediction and shows why a data-based pilot may not yet justify its cost.

Situation and problem

Illustrative scenario: a production business operates several similar pumps. Unexpected stoppages interrupt downstream work, while preventive replacement sometimes removes intact components. Some temperature readings are available, but maintenance notes are free text and timestamps do not always align. The result is a reaction to individual unusual readings rather than a traceable view of condition over time. The company, equipment and frequencies in this article are invented explanatory material. Before training a model, the team must distinguish a genuine technical fault from a normal change in load. Practical operating knowledge remains essential information rather than something a model automatically replaces.

Objectives for AI

You want unusual conditions highlighted early enough for a specialist to assess them during a suitable maintenance window. The first objective is not a failure time predicted to the minute. Define which pumps and operating modes are included and which protective alarms continue independently. Agree a maximum additional inspection workload, recording of false alarms and the lead time needed for a useful intervention. A possible pilot finding is more reliable prioritisation than today's thresholds. Claiming prevented downtime requires additional technical evidence and a longer observation period; one correct alert is not enough to establish that commercial outcome.

Possible AI solution

A possible architecture combines sensor readings with equipment state and confirmed maintenance history. Microsoft's reference architecture describes integrating real-time and contextual data. [1] In the proposed design, indicators for each operating mode are compared with simple threshold rules and then with an anomaly or classification model. MathWorks distinguishes fault detection from fault diagnosis using condition indicators. [2] The project must consequently not describe every unusual signal as a predicted failure. The interface displays the measurement trend, comparison condition and missing data. A generative language model is unnecessary for the core task; text summaries could at most be tested as an additional feature.

Workflow and practical implementation

Select two to four similar pumps and review their measurement points with maintenance staff. Correct timestamps, units and equipment identifiers. Mark stoppage, start-up, cleaning and normal load ranges without deriving this information from future events. Test historical events in chronologically separated data, then start several weeks of shadow operation. Give every alert a handling deadline and a responsible person. That person confirms a finding, rejects the alert or requests further measurements. Only the existing specialist approval creates a maintenance order. If data are unavailable, conventional maintenance planning remains authoritative instead of silently assuming that the machine is healthy.

Technical and organisational requirements

Technically, you need suitable sensors, synchronised timestamps and reliable mapping to equipment. Large data volumes cannot compensate for an uninformative condition measurement. If adequately documented faults are unavailable, an observational pilot may be more suitable than a supervised failure model. Production, maintenance and IT must agree terminology and responsibilities. Define data exports, sensor checks, network access and archiving of confirmed events. The first integration should be read-only and must not change machine settings. A designated owner decides when new components or altered operating conditions require renewed specialist validation. Build these responsibilities into normal maintenance routines rather than treating them as temporary project tasks.

Potential benefits and value

Possible benefits include a structured priority list, documented condition changes and better prepared maintenance discussions. Cleaning up equipment master data can be useful even when the AI model provides no additional value. Assess benefits through alerts actually handled, confirmed findings and additional investigation effort. A planned intervention is not automatically an avoided failure. For economic evidence, the team must assess plausible alternatives and potential consequential damage. If false alarms trigger unnecessary spare-part replacements, operations can become more expensive despite an attractive model metric. Include this countereffect in the pilot assessment and distinguish analytical performance from operational usefulness.

Effort, costs and economics

Own estimate: a limited pilot may take eight to twelve calendar weeks and 20–35 person-days, depending on instrumentation and data quality. No vendor prices are claimed. Hypothetical annual calculation: two genuinely avoidable four-hour stoppages valued at CHF 1,200 per hour produce CHF 9,600 gross benefit. An additional 24 inspection hours at CHF 85 cost CHF 2,040; assumed annual operation costs CHF 3,600. The calculated remainder is CHF 3,960. With CHF 24,000 initial expenditure, simple payback is approximately 6.1 years. Removing just one assumed benefit materially worsens the result. The pilot must investigate these assumptions rather than aim to validate a predetermined business case.

Privacy, risks and limitations

A high anomaly score is neither a diagnosis nor permission to omit a safety-relevant inspection. Rare faults, new pump types or moved sensors may lie outside training experience. Automatic control and shutdown are not part of this example. Protect operational information from unauthorised access and assess whether shift or individual identifiers are needed at all. Free-text notes should avoid unnecessary personal assessments. Agree access rights, reuse and deletion with external providers. Do not use the warning system to covertly assess staff performance. Existing safety and maintenance requirements remain applicable regardless of how convincing an analytical dashboard appears.

Success factors and recommendations

Start with a technically understood fault mode rather than the whole plant. Maintenance staff must be able to reject an alert with reasons; such feedback is more useful than routine confirmation. Compare additional value and false-alarm costs against existing thresholds. Document model versions, measurement changes and the operating modes last assessed. Suspend the trial when alerts are not handled on time, data fail or a critical finding remains unresolved. Plan a formal decision to continue, collect more data or stop. A negative pilot result may be the economically correct basis for the next maintenance investment rather than a project failure to conceal.

Sources and further reading

  1. Microsoft Learn – Predictive maintenance reference architecture, Fabric Real-Time IntelligenceAccessed on: 2026-11-23
  2. MathWorks – Detect and Diagnose Faults, Predictive Maintenance ToolboxAccessed on: 2026-11-23

Support from aresa

aresa can help structure failure consequences, available information and responsibilities, then derive a realistic pilot scope. Possible support includes process mapping, a benefit hypothesis, requirements for technical partners, data-quality assessment, a test plan and operational handover. Technical diagnosis and safety responsibility remain with your designated specialists. These activities describe possible support, not an already delivered aresa customer project. An initial workshop should establish which practical decision an earlier warning would change. Without that answer, more sensors or AI may not be the appropriate next investment. A smaller improvement to existing maintenance records may be preferable first.

Talk to aresa
aresa

From an idea to the right implementation.

Together, we explore where AI can help your business.

Talk to aresa